Young Africans SC president Eng. Hersi Said has explained the reasons behind the delay in starting construction of the club’s stadium, saying the club had to complete legal and administrative procedures before implementing the project in partnership with GSM Group.
Hersi said that despite Yanga announcing its partnership with GSM Group and reaching an investment agreement, construction could not begin immediately because several important procedures had to be completed regarding land ownership, members’ consent and the necessary permits. He explained that the club held several meetings with the Administrator General’s Office and submitted the required documents and explanations.
He added that, in seeking the best legal and operational framework to protect the interests of both the club and the investor, they had an opportunity to meet with the Attorney General and his team of experts. During the meeting, they were presented with an assessment and three possible options for implementing the project.
According to Hersi, one of the options involved establishing a business partnership through a Special Purpose Vehicle (SPV), supported by an investment agreement known as a Shareholders Agreement (SHA). He said this option had already been assessed by the Executive Committee and Board of Trustees, but the club also needed to consider the other two proposals presented by the government.
Hersi revealed that on November 17, 2026, the club received an official letter from the Administrator General outlining guidance on how to proceed with the project. After reviewing all three options and consulting the Board of Trustees, the Executive Committee agreed to proceed with the proposal to transfer ownership of the project land from the trustees’ ownership structure to Jangwani Complex Limited.
He said the government’s guidance focused on key measures to protect the interests of both Young Africans and GSM Group. The first was to ensure that the club’s land would not be used as collateral to secure loans or debts for the investor. Hersi emphasised that GSM Group had demonstrated its financial capacity and allocated resources for the stadium construction without relying on loans secured against Yanga’s land.
The second area involved separating the debts and business challenges of each party from the assets of the Jangwani Complex Limited project. Hersi explained that any financial difficulties Yanga might face in its other operations should not affect the project’s assets, and the same principle would apply to GSM Group. The objective is to ensure that the project company remains protected and operates under its own legal and financial framework.
Hersi stressed that these measures are intended to safeguard the club’s assets and ensure that the investment is implemented securely for the long term. He thanked the Attorney General’s Office and the Administrator General’s Office for their guidance and cooperation, noting that the project is highly significant to Yanga’s history and the development of football infrastructure in the country.